Ticket
| Projekt | RCM Ultimate |
|---|---|
| Zusammenfassung | Import hangs at 50%, if the option "Adjust section assignments before import" is checked |
| Sequenz | 1129 |
| Klassifikation | Bug |
| Priorität | High |
| Status | Done |
| Startdatum | 08.04.2013 |
| Fälligkeitsdatum | 08.04.2013 |
| Verantwortlich | |
| Version | 2.0.X |
| Aufwand | 0 |
| Beschreibung | If an event is imported and the option "Adjust section assignments before import" is checked, then the import itself hangs at around 50%. If this happens, RCM has to be closed by the TaskManager. |
Change history
| Zeitstempel | Wer | Änderung |
|---|---|---|
| 08.04.2013 13:15:46 | Ticket erstellt | |
| 08.04.2013 13:15:51 | Felix Romer | Feld: StatusAlter Wert: Opened Neuer Wert: Running |
| 08.04.2013 13:27:24 | Felix Romer | Feld: StatusAlter Wert: Running Neuer Wert: Done |